|
Portal Wheel Lathe: BHP Retrofit for productivity
BHP's Iron Ore Division, located at Port Hedland in Western
Australia, has one of Australia's largest privately owned rail networks.
The 426km single track railroad has built-in passing lanes to accommodate
up to 14 trains a day traveling at speeds of 75km an hour in combinations
of four to six powerful diesel locomotives and 320 ore cars.
For the trains to move over 60 million tonnes of iron ore each year
between the company's mines at Newman and the port facility at Port
Hedland, BHP must have total confidence in its ability to keep the
rolling stock in operation.
Like many Australian companies, BHP Iron Ore is continually seeking
to improve performance to better its position as a supplier of high
quality iron ore to an increasingly competitive international steel
industry. Safe, low-cost transport of iron ore is an integral part
of the company's ability to stay at the forefront of competition.
A key element in the maintenance of the rolling stock is the re-profiling
of wheel sets for the ore wagons. BHP had purchased a custom made
Portal Lathe for this purpose in 1992 from Hegenscheidt. The key
factor in the design of this prototype machine was the need for
a short cycle time in order to be able to handle the huge volume
of wheels required to be machined in BHP's ore car repair shop line.
This original machine control system was a SINUMERIK 850T and the
manufacturer had spent a number of years to customise the function
of the machine to BHP's needs.
After ten years of heavy work, in 2001, CNC Design was approached
to retrofit the machine with a new SINUMERIK system and to further
enhance its capability. CNC Design is responsible for SINUMERIK
support in Australia and other SE Asian countries.
Up to six sets of wheel sets are loaded into a magazine. The operator
enters information on the identification and status of the parts.
These are then automatically loaded one at a time into the portal
lathe where the wheel profile and back to back are measured. This
data is used to calculate the optimum metal machining cycle to return
the profile with minimum metal removal. The profiles may then be
re-measured to check conformance.
CNC Design offered a number of new possibilities including improved
part measurement, automatic tool measurement, tool force monitoring,
intelligent machining cycles, remote diagnostics and simplified
operator interface. The measured data was to be logged and transferred
to BHP's central database.
The project proceeded with the development of a new control system
based on the SINUMERIK 840D CNC system with 611D digital drives.
CNC Design has previous experience with development of measuring
and machining cycles for wheel profiling machines. This was further
developed to meet BHP's
specification.
The location, environment and machine availability for the project
presented unique issues. In the Pilbara the temperatures regularly
exceed 55 Degrees Centigrade and iron ore dust eventually covers
everything. Port Hedland is located in a remote region more than
4000 Km's from CNC Design's Melbourne office. The machine was only
available for 4-6 weeks for the retrofit. In short the project had
to be conducted under very difficult environmental conditions, in
a remote location and in a very short time.
CNC Design's Engineering team fully developed the system software
and simulated the operation of the machine. Valuable input into
profile measurement and machining was gained by involvement of the
Monash University Centre for Rail Technology, a world leader in
wheel life optimisation. The complete design for the six axis and
two spindle system was signed off by BHP before installation commenced.
Due to the location, it was necessary to provide spare parts and
all items necessary to the project to site. Installation of the
CNC system and drives and other equipment was completed in two weeks
and within four weeks the first wheel sets were machined. After
five weeks the machine was turned over
to production.
There have been significant benefits from this project. Part measurement
is faster, more accurate and gives a complete profile instead of
descrete points. The machining is better optimised with significant
costs savings due to better wheel usage. Automation of the tool
measurement, tool monitoring and part loading enable the machine
to run fully automatically.
|
|
machine back into production in 4-6 weeks |
| |
 |
| multiple
cutting technology for optimum cutting |
|
BHP are now so pleased with this project that they are planning
to further increase productivity by adding a pre-measurement
station and integrating the system into their SAP database.
Further reduction in cycle time is expected by the introduction
of RF tagging of the wheelsets. The wheelset ID will be automatically
picked up by the Siemens 840 system the Id number will then
be varified by SAP. Finally a file will automatically uploaded
to SAP with all pre and post machining details, providing
accurate data and reduction in man hours.
Overall this has been a very successfull CNC retrofit project.
Click here
for associated Recommendation Letter from the customer.
|
|