|
FIRST SIEMENS SIMODRIVE 611U SYSTEM FOR FORD KOMATSU TRANSFER PRESS
CNC Design Australia has just completed
a first for the Automotive Industry in Australia, in particular
for a Stamping Plant project in the South East Asia / Pacific region.
CNC Design was commissioned by the management of the Ford Geelong
Stamping Plant to retrofit a critical aspect of their Komatsu Transfer
Press.
The 'Roll-Over Arms' form a key component of this Komatsu Transfer
Press. The blanks are loaded onto the Roll-Over Arms once they come
out of the first press operation, as the wording suggests the blanks
is turned over 180 degree's and then fed into the transfer part
of the press for a further four pressing operations.
The problems faced by Ford from the old Servo Drive system was it's
lack of reliability, and also it took long periods to reset once
home positions, and reference points had been lost. Large amounts
of maintenance time was spent rectifying these problems. CNC Design
was asked to install a new Siemens Simodrive 611U system with S7
PLC that would integrate easily into the existing non-Siemens press
control.
New 1FT6 Servo Motors with brake, and absolute encoders were installed
to add stability and consistency to the system. With these type
of motors in place, referencing now became a simple, 'one button
push' function. A home position, soft limits, half cycles, manual
mode, auto mode, and braking speeds, where all established to provide
very simple easy to maintain functionality. The entire system was
built, tested, and pre-commissioned on it's own gear tray in our
Melbourne production area ready for a quick installation.
The key to the whole success of this project revolved around a project
schedule of 7 days over the Easter period. Ford could only provide
the Transfer Press for this short period of time. The completed
Simodrive system was installed by Ford personnel and then wired
to their existing control system. Commissioning was completed by
one of CNC Design's Project Engineers, Graeme Linsdell.
Once testing had been completed then went live and worked immediately,
final commissioning took less than a day. Referencing the motor's
is now just a simple matter of pressing the "home" button.
A problem area that used to take up to 20 minutes for three people
is now a simple function that takes one person only 5 seconds.
|
|